Combination Valve, Checking
Special tools and workshop equipment required
- Hand Vacuum Pump VAG1390
Test requirements
- No leaks in vacuum lines or hose connections.
- Vacuum hoses not clogged or kinked
- Connection hose between combination valves and pressure hose for Secondary Air Injection (AIR) Pump Motor not clogged or kinked.
- Ignition switched off.
Test sequence
-- Disconnect vacuum hose of combination valve to be checked:
- Combination valve, cylinder bank 1,
- Combination valve, cylinder bank 2.
Cylinder bank 1 = in driving direction, right.
Cylinder bank 2 = in driving direction, left.
-- Connect hand vacuum pump to corresponding vacuum connection of combination valve.
-- Remove pressure hose from connection line.
Do not use pressurized air for the following test!
-- Blow with light pressure into connection line.
Both combination valves must be closed.
-- Operate hand vacuum pump.
The respective combination valve must open.
If the combination valve does not open or it is constantly open:
-- Replace the respective combination valve:
- Combination valve, cylinder bank 1,
- Combination valve, cylinder bank 2.
-- Erase DTC memory of Engine Control Module (ECM), Diagnostic mode 4: Reset/erase diagnostic data.
-- Generate readiness code.