Installation [06/2016 - 03/2017]: Procedure
- INSTALL IGNITION OR STARTER SWITCH ASSEMBLY
- Install the 2 screws, and install the ignition or starter switch.
- Connect the connector.
- INSTALL UPPER STEERING COLUMN COVER
Refer to PROCEDURE - Step 5
- INSTALL LOWER STEERING COLUMN COVER
Refer to PROCEDURE - Step 6
- INSTALL NO. 1 INSTRUMENT PANEL UNDER COVER SUB-ASSEMBLY
Refer to PROCEDURE - Step 3
- INSTALL UPPER INSTRUMENT PANEL METER ORNAMENT
Refer to PROCEDURE - Step 5
- INSTALL METER HOOD SUB-ASSEMBLY
Refer to PROCEDURE - Step 6
- INSTALL INSTRUMENT PANEL ORNAMENT (w/ Large Ornament Panel)
Refer to PROCEDURE - Step 14
- INSTALL CENTER INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY (w/o Large Ornament Panel)
Refer to PROCEDURE - Step 15
- INSTALL INSTRUMENT SIDE PANEL RH
Refer to PROCEDURE - Step 7