Installation [08/2015 - 08/2019]: Procedure
- INSTALL POWER MANAGEMENT CONTROL ECU
- Attach the 2 claws to install the power management control ECU.
- INSTALL ECU INTEGRATION BOX RH
- Install the ECU integration box RH with the 2 nuts and bolt.
- Attach the clamp.
- Connect all the connectors.NOTE:
- Do not twist the connectors of the ECU when connecting them.
- Do not apply more force than necessary to the connectors. If more than 98 N (10 kgf, 22 lbf) of force is applied to a connector, the connector or connector holder may be damaged.
- INSTALL NO. 2 AIR DUCT SUB-ASSEMBLY
Refer to PROCEDURE - Step 4
- INSTALL LOWER INSTRUMENT PANEL SUB-ASSEMBLY
Refer to PROCEDURE - Step 14
- INSTALL INSTRUMENT PANEL BOX DOOR COVER
Refer to PROCEDURE - Step 15
- INSTALL LOWER NO. 2 INSTRUMENT PANEL AIRBAG ASSEMBLY
Refer to PROCEDURE - Step 1
- INSTALL LOWER INSTRUMENT COVER LH
Refer to PROCEDURE - Step 17
- INSTALL NO. 2 INSTRUMENT PANEL UNDER COVER SUB-ASSEMBLY
Refer to PROCEDURE - Step 18
- INSTALL NO. 2 INSTRUMENT CLUSTER FINISH PANEL GARNISH
HINT:
Use the same procedure described for the No. 1 instrument cluster finish panel garnish.
- Install the No. 2 instrument cluster finish panel garnish (Refer to PROCEDURE - Step 8 ).
- INSTALL COWL SIDE TRIM BOARD RH
- Attach the clip and claw to install the cowl side trim board.
- Install the clip.
- INSTALL DOOR SCUFF PLATE ASSEMBLY RH
- Attach the 4 clips, 10 claws and 2 guides to install the door scuff plate.
- CONNECT CABLE TO NEGATIVE BATTERY TERMINAL NOTE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected (Refer to INITIALIZATION [08/2015 - 08/2019] ).
- CHECK SRS WARNING LIGHT
- Check the SRS warning light (Refer to CHECK MODE PROCEDURE [08/2015 - ] ).