Transmission Control Cable: Installation

WARNING: This page is about a different variant/trim than selected.
  1. INSTALL TRANSMISSION CONTROL CABLE ASSEMBLY 
    NOTE: Before installing the transmission control cable assembly, check that the park/neutral position switch and the shift lever are in neutral.
    1. Put the transmission control cable into the cabin and connect the transmission control cable with the 2 nuts.

      Torque: 5.0 N*m (51 kgf*cm, 44 in.*lbf) 

      Fig 1: Locating Transmission Control Cable Assembly Nuts
      G06011538Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    2. Install the transmission control cable support with the nut.

      Torque: 5.0 N*m (51 kgf*cm, 44 in.*lbf) 

      Fig 2: Locating Transmission Control Cable Support With Nut
      G06011537Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    3. Connect the transmission control cable to the control cable bracket.
      Fig 3: Locating Control Cable Assembly
      G06008385Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    4. Connect the transmission control cable to the bracket with a new clip.
    5. Connect the transmission control cable assembly to the control shaft lever with the nut.

      Torque: 12 N*m (122 kgf*cm, 9 ft.*lbf) 

      Fig 4: Locating Transmission Control Cable Nut
      G06011483Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    6. Turn the nut of the transmission control cable 180° counterclockwise. While holding the nut in place, push in the stopper until the stopper clicks twice.
      Fig 5: Pushing Transmission Control Cable Stopper
      G06011525Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    7. Install the outer part of the transmission control cable to the shift lever retainer. Check that the spring is positioned at "A" and push in the stopper.
      Fig 6: Identifying Transmission Control Cable Installation Position
      G06011526Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002

      HINT:

      If the stopper cannot be pushed in, slightly turn the nut clockwise and then push in the stopper again.

    8. Push the 2 claws together at the top of the transmission control cable lock piece. While holding the 2 claws together, push the 2 lugs on the bottom of the lock piece toward each other and upward to pull out the lock piece.
      Fig 7: Pushing Transmission Control Cable Lock Piece
      G06011527Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    9. Install the cable end to the shift lever assembly.
      NOTE:
      • Check that the lock piece is pulled up.
      • Install the cable end all the way to the base of the pin.
        Fig 8: Locating Lock Piece
        G06043229Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    10. Push the lock piece into the adjuster case.
      NOTE: Securely push in the lock piece until it locks.
      Fig 9: Pushing Lock Piece Into Adjuster Case
      G06011529Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  2. INSTALL FRONT NO. 1 FLOOR HEAT INSULATOR 
    1. Install the front No. 1 floor heat insulator with the 3 nuts.

      Torque: 5.5 N*m (56 kgf*cm, 49 in.*lbf) 

      Fig 10: Locating Front No. 1 Floor Heat Insulator Nuts
      G06011533Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  3. INSTALL CENTER EXHAUST PIPE ASSEMBLY  (See INSTALLATION )
  4. INSTALL BATTERY CARRIER  (See INSTALLATION )
  5. INSTALL BATTERY  (See INSTALLATION )
  6. INSTALL AIR CLEANER CASE  (See INSTALLATION )
  7. INSTALL AIR CLEANER CAP SUB-ASSEMBLY  (See INSTALLATION )
  8. INSTALL NO. 1 ENGINE COVER SUB-ASSEMBLY  (See INSTALLATION )
  9. INSTALL LOWER CENTER INSTRUMENT PANEL FINISH PANEL  (See INSTALLATION )
  10. INSTALL FRONT NO. 1 CONSOLE BOX INSERT  (See INSTALLATION )
  11. INSTALL FRONT NO. 2 CONSOLE BOX INSERT  (See INSTALLATION )
  12. INSTALL FRONT CONSOLE BOX ASSEMBLY  (See INSTALLATION )
  13. INSTALL CONSOLE BOX CARPET 
  14. INSTALL NO. 2 SWITCH HOLE BASE  (See INSTALLATION )
  15. INSTALL FRONT UPPER CONSOLE BOX  (See INSTALLATION )
  16. INSTALL CENTER INSTRUMENT CLUSTER FINISH PANEL ASSEMBLY  (See INSTALLATION )
  17. INSTALL SHIFT LEVER KNOB SUB-ASSEMBLY  (See INSTALLATION )
  18. INSTALL CENTER INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY  (See INSTALLATION )
  19. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL  (See INSTALLATION )
  20. INSPECT SHIFT LEVER POSITION  (See ADJUSTMENT )
  21. ADJUST SHIFT LEVER POSITION  (See ADJUSTMENT )