AT Shift Lock Solenoid and "P" Range Switch: Inspection
| Step | Check | Yes | No |
|---|---|---|---|
| 1 CHECK SOLENOID UNIT. Measure the resistance of solenoid unit connector terminals. Terminals No. 4 - No. 3: |
Is the resistance 27.6 - 30.5 Ω? | Go to step 2. | Replace the solenoid unit. Refer to , AT SHIFT LOCK SOLENOID AND "P" RANGE SWITCH . |
| 2 CHECK SOLENOID UNIT. Connect the battery to the solenoid unit connector terminals, and then operate the solenoid. Terminals No. 3 (+) - No. 4 (-): |
Does the solenoid unit operate normally? | Go to step 3. | Replace the solenoid unit. Refer to , AT SHIFT LOCK SOLENOID AND "P" RANGE SWITCH . |
3 CHECK "P" RANGE SWITCH.
|
Is the resistance less than 1 Ω? | Go to step 4. | Replace the "P" range switch. Refer to , AT SHIFT LOCK SOLENOID AND "P" RANGE SWITCH . |
4 CHECK "P" RANGE SWITCH.
|
Is the resistance 1 MΩ or more? | Normal operation. | Replace the "P" range switch. Refer to , AT SHIFT LOCK SOLENOID AND "P" RANGE SWITCH . |