  1. Install the oil charge pipe with a new O-ring.
    NOTE: Use new bolts.

    Tightening torque: 

    38 N.m (3.9 kgf-m, 28.0 ft-lb) 

    Fig 1: Identifying Oil Charge Pipe And O-Ring
    G06342940Courtesy of SUBARU OF AMERICA, INC.
  2. Turn the turbine speed sensor 1 back to the original orientation, and install the bolt and connect the connector.

    Tightening torque: 

    7 N.m (0.7 kgf-m, 5.2 ft-lb) 

    Fig 2: Turbine Speed Sensor 1 Connector
    G00514655Courtesy of SUBARU OF AMERICA, INC.
  3. Install the front exhaust pipe.
  4. Install the under cover.
  5. Lower the vehicle.
  6. Connect the ground cable to battery.