Carburetor - MIKUNI 2-Bbl: Overhaul: Reassembly
- To assemble, reverse disassembly procedure. Install sub-EGR valve and verify proper operation. Install jet air control valve and tighten screws.
- When installing primary and secondary air bleed jets, and primary and secondary main jets, largest numbered jet should be installed on secondary side.
- When throttle body is completely assembled, and before installing on main body, check float level. See FLOAT LEVEL
adjustment procedure. Install choke cover and stake 4 screws in position. Tighten last screw with small hammer and pointed punch.
- Check alignment of punch mark with scribed line of pinion plate and punch mark of cam lever with Green paint mark of pinion plate gear. See Figure
and Fig 1
.
Courtesy of CHRYSLER MOTORS.