Inspection Procedure

  1. CHECK 12 V BATTERY TERMINALS CONNECTION 

    Check if 12 V battery terminals are clean and tight. Is the inspection result normal?

    YES>>

    GO TO 2.

    NO>>

    Repair 12 V battery terminals connection.

  2. CHECK "B" TERMINAL CONNECTION 

    Check if "B" terminal (generator ground harness) is clean and tight. Is the inspection result normal?

    YES>>

    GO TO 3.

    NO>>

    Repair "E" terminal connection.

  3. CHECK 12 V BATTERY STATUS 

    Check 12 V battery status. Refer to Work Flow . Is the inspection result normal?

    YES>>

    GO TO 4.

    NO>>

    Replace 12 V battery. Refer to Removal and Installation .

  4. CHECK DRIVE BELT TENSION 

    Check drive belt tension. Refer to Inspection . Is the inspection result normal?

    YES>>

    INSPECTION END

    NO>>

    Repair as needed.