Inspection Procedure

  1. CHECK BATTERY TERMINALS CONNECTION

    Check if battery terminals are clean and tight.

    Is the inspection result normal?

    YES 

    GO TO STEP 2  .

    NO 

    Repair battery terminals connection.

  2. CHECK FUSE

    Check for blown fuse and fusible link:

    WITH CUMMINS 5.0L

    Unit Power source (Power supply terminals) Fuse or Fusible Link
    Generator Battery (terminal 3) Fuse 70 (10 A)
    Battery (terminal 1) Fusible Link (250 A)
    Combination meter Ignition switch ON or START (terminal 2) Fuse 13 (10 A)
    WITH VK56VD

    Unit Power source (Power supply terminals) Fuse or Fusible Link
    Generator Battery (terminal 3) Fuse 66 (10 A)
    Battery (terminal 1) Fusible Link (250 A)
    Combination meter Ignition switch ON or START (terminal 2) Fuse 13 (10 A)

    Is the inspection result normal?

    YES 

    GO TO STEP 3  .

    NO 

    Be sure to eliminate cause of malfunction before installing new fuse or fusible link.

  3. CHECK GENERATOR GROUND TERMINAL CONNECTION

    Verify connector F201 (generator ground harness) terminal 5 is clean and tight.

    Is the inspection result normal?

    YES 

    GO TO STEP 4  .

    NO 

    Repair connection.

  4. CHECK DRIVE BELT TENSION

    Check drive belt tension. Refer to REMOVAL AND INSTALLATION: VK56VD .

    Is the inspection result normal?

    YES 

    Inspection End.

    NO 

    Repair as needed.