Cinch Latch Motor System Inspection
WARNING: This page is about a different car, the 2006 Nissan Quest. However, it is still accessible from the selected car via links, so may be relevant.
- CINCH LATCH MOTOR CIRCUIT INSPECTION
- Turn ignition switch OFF.
- Disconnect back door latch and back door control unit.
- Check continuity between back door latch (cinch latch motor) connector (B) D511 terminals 1, 2 and back door control unit connector (A) B55 terminals 11, 12.
1 - 12: Continuity should exist.
2 - 11: Continuity should exist.
- Check continuity between back door latch (cinch latch motor) connector (B) D511 terminals 1, 2 and ground.
1 - Ground: Continuity should not exist.
2 - Ground: Continuity should not exist.
OK or NG
OK: GO TO 2.
NG: Repair or replace harness.
- CINCH LATCH MOTOR OPERATION INSPECTION
Connect battery power to terminals 1 and 2 on the back door latch connector and check motor operation.
1 (+) - 2 (-): It operates.
1 (-) - 2 (+): It operates. (Reverse rotation)
OK or NG
OK: GO TO 3.
NG: Replace the back door latch.
- CINCH LATCH MOTOR SIGNAL INSPECTION
- Reconnect back door latch and back door control unit.
- While fully opening and closing the back door, check voltage waveform between back door control unit connector B55 terminals 11, 12 and ground using an oscilloscope.TERMINALS VOLTAGE REFERENCE
11 - Ground
12 - Ground
OK or NG
OK: Cinch latch motor circuit is OK.
NG: Replace the back door control unit.