LEMON Manuals: Even more car manuals for everyone
Home >> Mazda >> 2009 >> Tribute s Touring, FWD >> Repair and Diagnosis >> Engine Performance >> System >> Symptom Troubleshooting [Non-Hybrid Engine) >> Pinpoint Test 3: DTC P0620 - Generator Control Circuit >> Diagnostic Procedure

Diagnostic Procedure

NOTE:
  • Make sure battery voltage is greater than 12.2 volts prior to carrying out this pinpoint test.
NOTE:
  • Do not have a battery charger attached during vehicle testing.
DIAGNOSTIC PROCEDURE CHART

PINPOINT TEST 3 DTC P0620 - GENERATOR CONTROL CIRCUIT
STEP INSPECTION ACTION
1 CHECK THE BATTERY CONDITION
  • Carry out the Battery Condition Test to determine if the battery can hold a charge and is OK for use. See PINPOINT TEST 6: THE GENERATOR IS NOISY  .
  • Does the battery pass the condition test? 
Yes GO to the next step.
No INSTALL a new battery. See BATTERY REMOVAL/INSTALLATION . TEST the system for normal operation.
2 CHECK THE GENERATOR B+ CONNECTION
  • Key in OFF position.
  • Inspect generator 011-102A connection. Connector should be installed correctly and tight. Inspect the connector for bent and/or pushed-out pins.
  • Inspect generator 011-102B, circuit CABLE (R). Connection should be tight.
  • Measure the voltage between generator -102B, B+ circuit CABLE (R) and ground.
  • Are the generator connections OK and does the generator B+ measure battery voltage? 
Yes GO to the next step.
No REPAIR the generator connection or circuit. CLEAR the DTCs. REPEAT the self-test. TEST the system for normal operation.
3 CHECK THE VOLTAGE DROP IN THE B+ CIRCUIT (R)
  • Key in OFF position.
  • Connect: Generator 011-102A.
  • Start the engine.
  • With the engine running at idle, headlamps on and blower on high, measure the voltage drop between generator B+ -102B circuit CABLEPRO (R) and the positive battery terminal.
  • Is the voltage drop less than 0.5 volt? 
Yes GO to the next step.
No REPAIR the circuit B+ CABLE (R) and the positive battery cable for loose connections, physical damage or wire corrosion. CLEAR the DTCs. REPEAT the self-test. TEST the system for normal operation.
4 A SENSE CIRCUIT LOAD TEST
  • Disconnect: Generator-102A.
  • Key in ON position.
  • Using a 12-volt test lamp connected to ground, check for voltage at generator 011-102A pin 3, circuit (BR/R) harness side.
  • Does the test lamp illuminate? 
Yes GO to the next step.
No VERIFY Battery Junction Box (BJB) fuse 6 (15A) is OK. If OK, REPAIR circuit (BR/R). If not OK, REFER to the appropriate SYSTEM WIRING DIAGRAMS article to identify the possible causes of the circuit short. CLEAR the DTCs. REPEAT the self-test. TEST the system for normal operation.
5 CHECK THE GENERATOR COMMAND LINE FAULT (GENCMD_LF) PID
NOTE:
  • Many of the PCM PIDs selected will be monitored later in this pinpoint test.
  • Select and monitor the following PCM PIDs: Generator Monitor (GENMON).
    • Generator Command (GENCMD).
    • Generator Command Line Fault (GENCMD_LF).
  • With the engine still running at idle, monitor the GENCMD_LF PID.
  • Is the GENMON_LF PID ON? 
Yes GO to the next step.
No GO to step 9.
6 CHECK THE GENCOM CIRCUIT FOR A SHORT TO POWER
  • Key in OFF position.
  • Disconnect: Generator 011-102A.
  • Key in ON position.
  • Measure the voltage between generator -102A pin 2, circuit (LAD), harness side and ground.
  • Does voltage read 1 volt or less? 
Yes GO to the next step.
No GO to step 11.
7 COMPARE THE PCM PIDs GENERATOR MONITOR (GENMON) AND GENERATOR COMMAND (GENCMD)
  • Key in OFF position.
  • Connect a fused jumper wire between generator -102A pin 1, circuit (V), harness side and generator -102A pin 2, circuit (L/O), harness side.
  • Start the engine.
  • Monitor the GENMON and GENCMD PIDs while carrying out a wiggle test on the generator harness.
  • Does the GENMON PID read within 5% of the GENCMD PID? 
Yes GO to the next step.
No GO to step 12.
8 CHECK CIRCUIT (L/O) FOR DAMAGE OR AN OPEN
  • Key in OFF position.
  • Disconnect: PCM -175B.
  • Inspect the following harness connectors for damaged or pushed-out pins:
    • PCM -175B pin 53, circuit (L/O).
    • Generator -102B pin 2, circuit (L/O).
  • Measure the resistance between PCM -175B pin 53, circuit (L/O), harness side and generator -102A pin 2, circuit (L/O), harness side.
  • Are the connectors and pins free of damage and is the resistance less than 5 ohms? 
Yes GO to the next step.
No REPAIR circuit (L/O). CLEAR the DTCs. REPEAT the self-test. TEST the system for normal operation.
9 CHECK CIRCUIT (L/O) FOR SHORT TO GROUND
  • Key in OFF position.
  • Disconnect: Generator -102A (if not previously disconnected).
  • Measure the resistance between the generator -102A pin 2, circuit (L/O), harness side and ground.
  • Enter the following diagnostic mode on the scan tool: Retrieve PCM DTCs.
  • Is the resistance greater than 10,000 ohms? 
Yes GO to the next step.
No REPAIR the circuit. CLEAR the DTCs. REPEAT the self-test. TEST the system for normal operation.
10 CHECK THE CHARGING SYSTEM CIRCUITS FOR INTERMITTENT FAULTS
  • Connect: Generator 011-102A.
  • Connect: PCM -175B.
  • Key in ON position.
  • Clear all DTCs.
  • Start the engine and let the engine run for 5 minutes.
  • Retrieve continuous memory DTCs from all modules.
  • Are any charging system DTCs stored into memory? 
Yes INSTALL a new generator. See GENERATOR REMOVAL/INSTALLATION - 2.5L or GENERATOR REMOVAL/INSTALLATION - 3.0L .
No The fault is not present at this time. This may indicate an intermittent fault. CARRY OUT a wiggle test on the charging system circuits to try and RECREATE the concern. CHECK generator connections for corrosion, loose connections and/or bent terminals. REPAIR as necessary. CLEAR the DTCs. REPEAT the self-test. TEST the system for normal operation.
11 CHECK FOR SHORT TO VOLTAGE
  • Key in OFF position.
  • Disconnect: PCM -175B.
  • Key in ON position.
  • Measure the voltage between generator -102A pin 2, circuit (L/O), harness side and ground.
  • Does the voltage read 0 volt? 
Yes INSTALL a new PCM. See POWERTRAIN CONTROL MODULE (PCM) REMOVAL/INSTALLATION - 2.5L or POWERTRAIN CONTROL MODULE (PCM) REMOVAL/INSTALLATION - 3.0L . CLEAR the DTCs. REPEAT the self-test. TEST the system for normal operation.
No REPAIR circuit (L/O). CLEAR the DTCs. REPEAT the self-test. TEST the system for normal operation.
12 INSPECT GENERATOR CIRCUITS
  • Key in OFF position.
  • Disconnect: PCM C175B.
  • Inspect the following connector pins for damage and/or corrosion, PCM ground -175B pin 69, circuit (B), generator -102A pin 1, circuit (V), and generator -102A pin 2, circuit (L/O).
  • Are the connectors OK? 
Yes INSTALL a new PCM. See POWERTRAIN CONTROL MODULE (PCM) REMOVAL/INSTALLATION - 2.5L or POWERTRAIN CONTROL MODULE (PCM) REMOVAL/INSTALLATION - 3.0L . CLEAR the DTCs. REPEAT the self-test. TEST the system for normal operation.
No REPAIR high resistance or loose connections in the affected circuit(s). CLEAR the DTCs. REPEAT the self-test. TEST the system for normal operation.