Installation [11/2017 - 01/2023]: Procedure
- INSTALL MULTI-DISPLAY ASSEMBLY
- INSTALL NO. 1 MULTI-DISPLAY BRACKET
- Install the No. 1 multi-display bracket with the 2 screws.
- INSTALL MULTI-DISPLAY ASSEMBLY WITH BRACKET
- INSTALL INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY
Refer to PROCEDURE - Step 13 [11/2017 - 03/2019] , or refer to PROCEDURE - Step 13 [03/2019 - 09/2020] , or refer to PROCEDURE - Step 13 [09/2020 - 01/2023]
- INSTALL METER HOOD SUB-ASSEMBLY
Refer to PROCEDURE - Step 31 [11/2017 - 03/2019] , or refer to PROCEDURE - Step 31 [03/2019 - 09/2020] , or refer to PROCEDURE - Step 31 [09/2020 - 01/2023]
- INSTALL LOWER INSTRUMENT PANEL FINISH PANEL SUB-ASSEMBLY
Refer to PROCEDURE - Step 34 [11/2017 - 03/2019] , or refer to PROCEDURE - Step 34 [03/2019 - 09/2020] , or refer to PROCEDURE - Step 34 [09/2020 - 01/2023]
- CONNECT HOOD LOCK CONTROL LEVER SUB-ASSEMBLY
Refer to PROCEDURE - Step 35 [11/2017 - 03/2019] , or refer to PROCEDURE - Step 35 [03/2019 - 09/2020] , or refer to PROCEDURE - Step 35 [09/2020 - 01/2023]
- INSTALL NO. 1 INSTRUMENT PANEL UNDER COVER SUB-ASSEMBLY
Refer to PROCEDURE - Step 36 [11/2017 - 03/2019] , or refer to PROCEDURE - Step 36 [03/2019 - 09/2020] , or refer to PROCEDURE - Step 36 [09/2020 - 01/2023]
- CONNECT CABLE TO NEGATIVE BATTERY TERMINAL NOTE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected.
Refer to INITIALIZATION [11/2017 - 03/2019] , or refer to INITIALIZATION [03/2019 - 01/2023]
- CUSTOMIZE POWER TILT AND POWER TELESCOPIC STEERING COLUMN SYSTEM (for Power Tilt and Power Telescopic Steering Column)
Refer to PROCEDURE - Step 15 [09/2014 - 03/2019] , or refer to PROCEDURE - Step 15 [03/2019 - ]