Installation [07/2015 - ]: Procedure
- INSTALL SPARK PLUG
- Install the 6 spark plugs.
Torque: 18 N*m (184 kgf*cm, 13 ft.*lbf)
HINT:
Perform "Inspection After Repair" after replacing a spark plug (Refer to INITIALIZATION [07/2015 - ] ).
- Install the 6 spark plugs.
- INSTALL IGNITION COIL ASSEMBLY
- Install the 6 ignition coil assemblies with the 6 bolts.
Torque: 10 N*m (102 kgf*cm, 7 ft.*lbf)
HINT:
Perform "Inspection After Repair" after replacing an ignition coil assembly (Refer to INITIALIZATION [07/2015 - ] ).
- Connect the 6 ignition coil assembly connectors.
- Connect the 2 wire harness clamps.
- Install the nut.
Torque: 8.0 N*m (82 kgf*cm, 71 in.*lbf)
- Install the 6 ignition coil assemblies with the 6 bolts.
- INSTALL NO. 1 SURGE TANK STAY
Refer to PROCEDURE - Step 19
- INSTALL INTAKE AIR SURGE TANK ASSEMBLY
Refer to INSTALLATION [07/2015 - ]