Floor Shift Assembly: Installation

WARNING: This page is about a different car, the 2008 Lexus GS 460. However, it is still accessible from the selected car via links, so may be relevant.
  1. INSTALL TRANSMISSION FLOOR SHIFT ASSEMBLY 
    1. Install the floor shift assembly with the 4 bolts.
      NOTE: Do not allow the wire harness to get caught between the parts.

      Torque: 8.3 N*m (85 kgf*cm, 74 in.*lbf) 

    2. Connect the 6 clamps to the floor shift assembly.
    3. Connect the 2 connectors to the floor shift assembly.
      Fig 1: Locating Transmission Floor Shift Assembly, Clamps And Connector
      G05806441Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  2. INSTALL FLOOR SHIFT GEAR SHIFTING ROD SUB-ASSEMBLY 
    1. Turn the control shaft lever of the neutral start switch counterclockwise until it stops, and turn it clockwise 2 notches to set it to the N position.
      Fig 2: Turning Control Shaft Lever
      G05750903Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    2. Move the shift lever to the N position and tighten the nut while lightly pushing the lever toward the R position.

      Torque: 13 N*m (130 kgf*cm, 9 ft.*lbf) 

      NOTE: Do not push the shift lever too hard.
  3. INSTALL FRONT FLOOR NO. 1 HEAT INSULATOR  (See INSTALLATION )
  4. INSTALL FRONT EXHAUST PIPE ASSEMBLY  (See REMOVAL )
    Fig 3: Locating Floor Shift Gear Shifting Rod Nut
    G05806440Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  5. CONNECT HEATED OXYGEN SENSOR (for Bank 2 Sensor 2)  (See INSTALLATION )
  6. CONNECT HEATED OXYGEN SENSOR (for Bank 1 Sensor 2)  (See INSTALLATION )
  7. INSTALL FRONT FLOOR COVER CENTER LH  (See INSTALLATION )
  8. INSTALL FRONT FLOOR COVER CENTER RH 
    1. Install the front floor cover center RH with the 3 grommets.

      Torque: 5.4 N*m (55 kgf*cm, 48 in.*lbf) 

  9. INSTALL REAR NO. 1 FLOOR PANEL BRACE  (See INSTALLATION )
  10. INSTALL FRONT FLOOR BRACE CENTER  (See INSTALLATION )
    Fig 4: Locating Front Floor Cover Center RH And Grommets
    G05305021Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  11. INSTALL NO. 2 CONSOLE BOX DUCT  (See INSTALLATION )
  12. INSTALL CONSOLE BOX ASSEMBLY  (See INSTALLATION )
  13. INSTALL CONSOLE BOX REGISTER ASSEMBLY  (See INSTALLATION )
  14. INSTALL CONSOLE BOX PLATE  (See INSTALLATION )
  15. INSTALL INSTRUMENT PANEL FINISH PANEL END LH  (See INSTALLATION )
  16. INSTALL INSTRUMENT PANEL FINISH PANEL END RH  (See INSTALLATION )
  17. INSTALL UPPER CONSOLE PANEL ASSEMBLY  (See INSTALLATION )
  18. INSTALL FRONT CONSOLE UPPER PANEL GARNISH  (See INSTALLATION )
  19. INSTALL SHIFT LEVER KNOB 
    1. Install the shift lever knob and turn it in the direction indicated by the arrow.
  20. ADJUST SHIFT LEVER POSITION  (See ADJUSTMENT  )
  21. INSPECT FOR EXHAUST GAS LEAK 
    Fig 5: Installing Shift Lever Knob
    G05806474Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002