LEMON Manuals: Even more car manuals for everyone
Home >> International >> 1975 >> Scout II 3.2L Eng, RWD >> Labor Times >> Other Variant >> Engine Mechanical >> Mechanical >> Engine Assembly >> Removal & Installation

Removal & Installation

WARNING: This page is about the Scout II 3.2L Eng, 4WD, which is a different variant/trim than selected.
Includes: R&I only those components necessary for the removal of the complete Engine Assembly. DOES NOT include transfer components or tune Engine.

Applies ToNoteStandard HoursWarranty HoursSkill Level
In-Line4,Standard Trans,Gas7.15.7C
Additional Procedure: ENGINE ASSEMBLY: Removal & Installation:
Where Air Cond interferes add0.60.6C
Where Air Pump interferes add0.9C
Where Power Steering interferes add0.30.3C