Includes: Remove carbon, check surfaces for warpage, reface or replace Valves, resurface Valve Seats and clean Valve Guides. Adjust Valves (where applicable).

Applies ToNoteStandard HoursWarranty HoursSkill Level
In-Line6,Gas8.0A
Combination Procedure: ROCKER ARM ASSEMBLY: Disassemble & Assemble:
Includes: Clean and replace necessary components only.
In-Line60.6B
Combination Procedure: VALVE GUIDE: Remove & Replace:
Each0.1A
Combination Procedure: VALVE SEAT INSERT: Remove & Replace:
Each Additional0.2A
One0.6A