Diagnostic Procedure
- INSPECTION START
Start engine.
Is engine running?
Yes or No
- Yes: GO TO 7.
- No: GO TO 2.
- CHECK POWER SUPPLY CIRCUIT FOR ECM CIRCUIT-I
- Turn ignition switch OFF and then ON.
- Check voltage between ECM terminal 109 and ground with CONSULT-II or tester.
Voltage: Battery voltage
OK or NG
- OK: GO TO 4.
- NG: GO TO 3.
- DETECT MALFUNCTIONING PART
Check the following.
- Harness connectors M72, F102
- Fuse block (J/B) connector M4
- 10A fuse
- Harness for open or short between ECM and fuse
- : Repair harness or connectors.
- CHECK ECM GROUND CIRCUIT FOR OPEN AND SHORT-I
- Turn ignition switch OFF.
- Disconnect ECM harness connector.
- Check harness continuity between ECM terminals 1, 115, 116 and ground.
Refer to WIRING DIAGRAM .
Continuity should exist.
- Also check harness for short to power.
OK or NG
- OK: GO TO 6.
- NG: GO TO 5.
- DETECT MALFUNCTIONING PART
Check the following.
- Joint connector-4
- Harness connectors F102, M72
- Harness for open or short between ECM and ground
- : Repair open circuit or short to power in harness or connectors.
- CHECK POWER SUPPLY CIRCUIT FOR ECM CIRCUIT-II
- Reconnect ECM harness connector.
- Turn ignition switch ON.
- Check voltage between IPDM E/R terminal 35 and ground with CONSULT-II or tester.
Voltage: Battery voltage
OK or NG
- OK: Go to "IGNITION SIGNAL ".
- NG: GO TO 7.
- CHECK POWER SUPPLY CIRCUIT FOR ECM CIRCUIT-III
- Turn ignition switch ON and then OFF.
- Check voltage between ECM terminals 119, 120 and ground with CONSULT-II or tester.
Voltage: After turning ignition switch OFF, battery voltage will exist for a few seconds, then drop approximately 0V.
OK or NG
- CHECK POWER SUPPLY CIRCUIT FOR ECM CIRCUIT-V
- Turn ignition switch OFF.
- Check voltage between ECM terminal 111 and ground with CONSULT-II or tester.
Voltage: Battery voltage
OK or NG
- OK: GO TO 9.
- NG: GO TO 11.
- CHECK POWER SUPPLY CIRCUIT FOR ECM CIRCUIT-VI
- Disconnect ECM harness connector.
- Disconnect IPDM E/R harness connector E8.
- Check harness continuity between ECM terminals 119, 120 and IPDM E/R terminal 33.
Refer to WIRING DIAGRAM .
Continuity should exist.
- Also check harness for short to ground and short to power.
OK or NG
- OK: GO TO 14.
- NG: GO TO 10.
- DETECT MALFUNCTIONING PART
Check the following.
- Joint connector-3
- Joint connector-4
- Harness or connectors E12, F3
- Harness for open or short between ECM and IPDM E/R
- : Repair open circuit or short to ground or short to power in harness or connectors.
- CHECK POWER SUPPLY CIRCUIT FOR ECM CIRCUIT-VII
- Disconnect ECM harness connector.
- Disconnect IPDM E/R harness connector.
- Check harness continuity between ECM terminal 111 and IPDM E/R terminal 44.
Refer to WIRING DIAGRAM .
Continuity should exist.
- Also check harness for short to ground and short to power.
OK or NG
- OK: GO TO 13.
- NG: GO TO 12.
- DETECT MALFUNCTIONING PART
Check the following.
- Harness or connectors E11, F2
- Harness for open or short between ECM and IPDM E/R
- : Repair open circuit or short to ground or short to power in harness or connectors.
- CHECK 15A FUSE
- Disconnect 15A fuse from IPDM E/R.
- Check 15A fuse.
OK or NG
- OK: GO TO 16.
- NG: Replace 15A fuse.
- CHECK ECM GROUND CIRCUIT FOR OPEN AND SHORT-II
- Check harness continuity between ECM terminals 1, 115, 116 and ground.
Refer to WIRING DIAGRAM .
Continuity should exist.
- Also check harness for short to power.
OK or NG
- OK: GO TO 16.
- NG: GO TO 15.
- Check harness continuity between ECM terminals 1, 115, 116 and ground.
- DETECT MALFUNCTIONING PART
Check the following.
- Joint connector-4
- Harness or connectors F102, M72
- Harness for open or short between ECM and ground
- : Repair open circuit or short to power in harness connectors.
- CHECK INTERMITTENT INCIDENT
Refer to "TROUBLE DIAGNOSIS FOR INTERMITTENT INCIDENT ".
OK or NG
- OK: Replace IPDM E/R. Refer to REMOVAL AND INSTALLATION OF IPDM E/R in IPDM E/R (INTELLIGENT POWER DISTRIBUTION MODULE ENGINE ROOM) - G35 COUPE article. .
- NG: Repair open circuit or short to ground or short to power in harness or connectors.