VTC Oil Control Solenoid Valve Removal/Test/Installation

  1. Disconnect the VTC oil control solenoid valve 2P connector (A).
    Fig 1: VTC Oil Control Solenoid Valve And 2P Connector With Torque Specifications
    G07341665Courtesy of AMERICAN HONDA MOTOR CO., INC.
  2. Remove the bolt (B) and the VTC oil control solenoid valve (C).
  3. Connect VTC oil control valve 2P connector terminal No. 2 to the battery positive terminal with a jumper wire. Connect VTC oil control solenoid valve 2P connector terminal No. 1 to the battery negative terminal with a jumper wire.
    Fig 2: Connecting VTC Oil Control Valve 2P Connector Terminal No. 2 To Battery Positive Terminal With Jumper Wire
    G07341666Courtesy of AMERICAN HONDA MOTOR CO., INC.
  4. Measure the clearance of the valve (A). The clearance should be at least 0.05 in (1.2 mm)
    • If the clearance is as specified, the valve is OK; reinstall it with a new O-ring (B).
    • If the clearance is not as specified, install a new valve and O-ring.
      NOTE:
      • Before you install the valve, make sure its mating surface to the cylinder head is clean and dry.
      • Coat the O-ring with engine oil before you install it.
      • Do not install the valve while wearing cloth fibrous gloves. Be careful not to contaminate the cylinder head opening.
        Fig 3: Measuring Clearance Of Valve
        G07341667Courtesy of AMERICAN HONDA MOTOR CO., INC.