Shift Cable: Installation
- Ensure the transmission is in the mechanical Neutral position. Following the shift cable adjustment procedure, install the shift cable end of the shift cable to the transmission shift lever stud ball. See SHIFT CABLE
under ADJUSTMENTS.
- Install the retainer to the shift cable and transmission bracket. Feed the shift cable through the floor panel. See Fig 2
. Lower the vehicle.
- Install the tape and grommet on the shift cable to the floor panel. Install the retainer securing the shift cable to the shift controller. See Fig 1
.
- Install the console. See appropriate SHIFT INTERLOCK SYSTEMS article in AUTOMATIC TRANSMISSIONS. Install the front mat and carpet.
Courtesy of GENERAL MOTORS CORP.
Courtesy of GENERAL MOTORS CORP.
Courtesy of GENERAL MOTORS CORP.