Grind Complete
Includes: Remove carbon, check surfaces for warpage, reface or replace Valves, resurface Valve Seats and clean Valve Guides. Adjust Valves (where applicable).
| Applies To | Note | Standard Hours | Warranty Hours | Skill Level |
| C1500,In-Line6,4.1L Eng, Air Pump System | | 8.5 | 5.6 | A |
| RWD,In-Line6,4.1L Eng, Pulse Air System | | 8.7 | 5.8 | A |
| Additional Procedure: VALVE: Grind Complete: |
| In-Line6, Where Air Cond interferes add | | 0.3 | 0.3 | A |
| In-Line6, Where Pwr Strg interferes add | | 0.3 | 0.3 | A |
| Where Air Pump interferes add | | 0.2 | | A |
| Where Cruise Control interferes add | | 0.2 | | A |
| Where Elect Eng System interferes add | | 0.5 | | A |
| Combination Procedure: ROCKER ARM STUD: Remove & Replace: |
| Each Additional | | 0.2 | | B |
| One | | 0.3 | | B |
| Combination Procedure: VALVE LIFTERS: Remove & Replace: |
| In-Line6, All | | 0.4 | | B |
| Combination Procedure: VALVE LIFTERS (REMOVED): Clean: |
| Each Additional | | 0.1 | | B |
| One | | 0.2 | | B |