Smart Junction Box (SJB): Installation
WARNING: This page is about a different car, the 2007 Ford Ranger. However, it is still accessible from the selected car via links, so may be relevant.
- Install the SJB.
- Install the 3 screws.
- Connect the electrical connectors.
- Install the RH lower cowl trim panel. For additional information, refer to INTERIOR TRIM AND ORNAMENTATION article.
- Connect the battery. For additional information, refer to BATTERY, MOUNTING AND CABLES article.
- Download the SJB configuration information from the scan tool. For additional information, refer to MODULE CONFIGURATION article, PMI.
- Carry out TPMS sensor training. For additional information, refer to WHEELS AND TIRES article.
NOTE:
When successful, this step clears the manufacturing mode DTCs.