RADIATOR, Engine Cooling: Installation: Radiator

WARNING: This page is about a different car, the 2010 Dodge Avenger and 2010 Chrysler Sebring. However, it is still accessible from the selected car via links, so may be relevant.
Fig 1: A/C LINE
GC0120904Courtesy of CHRYSLER LLC
1 - A/C LINE
2 - SUPPORT BRACKET
  1. Position the A/C condenser onto the radiator.
  2. Slide the radiator/condensor assembly into position and seat the radiator assembly lower rubber isolators in the mount holes.
  3. Install the mounting brackets to the upper core support using two torx screws.
  4. Install A/C lines to condenser/cooler.
  5. Install transmission oil cooler tubes support bracket to radiator (2). Tighten mounting screws to 5 N.m (45 in. lbs.).
  6. Position radiator cooling fans on radiator.
    Fig 2: UPPER RADIATOR HOSE
    GC0120903Courtesy of CHRYSLER LLC
    1 - ELECTRICAL CONNECTOR
    2 - UPPER RADIATOR HOSE
  7. Connect cooling fan electrical connector (1).
  8. Install upper and lower radiator hoses at radiator.
  9. Install the grille. Refer to Body/Exterior/GRILLE - Installation
  10. Install front bottom splash shield (if equipped).
  11. Install under belly pan (if equipped).
  12. Fill cooling system. See Cooling - Standard Procedure .
  13. Charge A/C system. Refer to Heating and Air Conditioning/Plumbing - Standard Procedure .
  14. Install air box assembly.
  15. Connect negative battery cable.
  16. Install engine cover.