Shift Cable: Installation
- Install the select lever assembly.
- Install the select indicator assembly.
- Install the knob. Install the 2 knob screws.
- Place the manual shift lever in the LOW position.
- Install the shift select cable (4) into the shift select cable bracket at the transmission. See Figure .
- Secure the shift select cable (4).
- Install the shift select cable into the manual shift lever while moving the manual shift lever back to the Neutral position.NOTE: Do not fully tighten the lock nut.
- Secure the shift select cable with the select cable lock nut (3). Tighten the shift select cable lock nut to specification. See TORQUE SPECIFICATIONS .
- Lower the vehicle. Make it possible to access both the manual selector and the manual shift lever.
- Install the shift select cable to the selector lever. See Figure .
- Secure the washer with the retaining clip.
- Inspect both ends of the shift select cable to ensure that no cable deflection exists.
- Lower the vehicle.
- Install the manual selector to the floor.
- Secure the manual selector to the floor with the 4 bolts. Tighten the manual selector bolts to specification. See TORQUE SPECIFICATIONS .
- Install the shift indicator lamp (1).
- Install the shift lock solenoid electrical connector (3) under the carpet.
- Install the console box to the floor. Install the 4 screws (1, 3, 4 and 6) and the 2 plastic retaining clips. See Figure .
- Put the manual selector in the Park position.
- Connect the negative battery cable. Check for proper operation.